MS Project - can a resource hourly cost change in mid-project and project maintains complete history?

To be more explicit: at the beginning of a project a resource is entered at $20 per hour. Half way through the project the same resource is now entered at $50 per hour. Can MS Project show both hourly costs for the same resource and when the change occurred? If so, how is this accomplished?



Thanks,

Marty MartinMS Project - can a resource hourly cost change in mid-project and project maintains complete history?Yes. Go to the resource sheet view, and double-click on a resource to bring up the resource information dialogue box. Click on the costs tab, and look at the bottom part of the dialogue box. You will see a table into which you can enter different rates, and the dates the rates become effective.